Before you fall for a floor plan, we walk the lot and the numbers. I'm a project manager at H&H Construction, so I spend my days on the parts a rendering leaves out: utilities, setbacks, and how long things take once winter shows up.
Lot first
Start with the dirt. Is there city water and sewer at the lot line, or will you need a well and septic? Where are the setbacks and easements? How does the lot drain, and what's the soil like? Is there an HOA or covenants that control the house size, materials, or fences? Is it in a city or a township, and who issues the permits?
Then look at what homes nearby have sold for. That number matters later.
Plan for now and for later
Build for how you live, but keep an eye on how a buyer would see it someday. Bedroom count, garage size, a main-floor laundry, and storage all come up again when you sell. A layout that only works for you can cost you at resale.
Reading builder bids line by line
Two bids for the same plan can look far apart and end up close once you line them up. Compare:
- Allowances for cabinets, counters, flooring, lighting, and appliances
- Site work: excavation, grading, driveway, sod or seed, landscaping
- Utility hookups, permit fees, and surveys
- How change orders are priced
- The draw schedule
- The written schedule, and what happens if it slips
Low allowances make a bid look cheap until you start picking finishes.
Timelines people underestimate
A schedule on paper assumes everything shows up on time. Here's where it usually moves:
- Selections. Cabinets, counters, and fixtures have lead times. Late decisions push everything behind them.
- Weather. Exterior work slows when the ground freezes. Concrete poured in cold weather needs heat and blankets, which adds cost.
- Inspections. Each stage waits for an inspection before the next one starts.
- Trade calendars. Good contractors book out. In April 2026, H&H was 60 to 90 days out on deck builds.
Ask every builder for a written schedule, and ask what they've seen push it.
Know the warranty
Minnesota gives new homes a statutory warranty under Minnesota Statutes chapter 327A: one year for defects from faulty workmanship and materials, two years for faulty installation of plumbing, electrical, heating, and cooling, and ten years for major construction defects. Read the builder's written warranty too, and ask how claims are handled.
Resale value before you pour
Before you sign, compare what the finished house should be worth with the resale homes around it. If you're building far above what the street will pay, you may not get it back when you sell. I'll pull the sales.
Build or buy this year?
Buying a resale is usually faster, with a known closing date. Building gets you the layout and finishes you want, with more decisions and more ways for the schedule to move. If the house you need doesn't exist in what's for sale, building makes sense. If it does, buy it and update over time. More on the Build page, and if you're comparing towns, see Kasson vs Rochester.
Text me the lot or the plan you're looking at. We'll go through it before you commit.